| 2005 | 1 | Co-gen Electricity | 1,532.85 |
| 2005 | 1 | Co-gen Steam | 1,533.07 |
| 2005 | 1 | Other On-Campus Stationary | 8,374.33 |
| 2005 | 1 | Direct Transportation | 184.60 |
| 2005 | 1 | Refrigerants & Chemicals | 376.34 |
| 2005 | 2 | Purchased Electricity | 4,023.91 |
| 2005 | 3 | Directly Financed Air Travel | 1,638.21 |
| 2005 | 3 | Solid Waste | -26.13 |
| 2005 | 3 | T&D Losses | 397.97 |
| 2006 | 1 | Co-gen Electricity | 3,246.07 |
| 2006 | 1 | Co-gen Steam | 3,246.49 |
| 2006 | 1 | Other On-Campus Stationary | 6,724.84 |
| 2006 | 1 | Direct Transportation | 187.30 |
| 2006 | 1 | Refrigerants & Chemicals | 259.96 |
| 2006 | 2 | Purchased Electricity | 1,339.16 |
| 2006 | 3 | Directly Financed Air Travel | 1,677.29 |
| 2006 | 3 | Solid Waste | -24.64 |
| 2006 | 3 | T&D Losses | 132.44 |
| 2007 | 1 | Co-gen Electricity | 3,333.44 |
| 2007 | 1 | Co-gen Steam | 3,331.82 |
| 2007 | 1 | Other On-Campus Stationary | 6,871.43 |
| 2007 | 1 | Direct Transportation | 188.33 |
| 2007 | 1 | Refrigerants & Chemicals | 159.80 |
| 2007 | 2 | Purchased Electricity | 1,160.27 |
| 2007 | 3 | Directly Financed Air Travel | 1,538.29 |
| 2007 | 3 | Solid Waste | -20.88 |
| 2007 | 3 | T&D Losses | 114.75 |
| 2008 | 1 | Co-gen Electricity | 1,319.68 |
| 2008 | 1 | Co-gen Steam | 1,319.89 |
| 2008 | 1 | Other On-Campus Stationary | 5,666.87 |
| 2008 | 1 | Direct Transportation | 169.19 |
| 2008 | 1 | Refrigerants & Chemicals | 251.37 |
| 2008 | 2 | Purchased Electricity | 3,552.86 |
| 2008 | 3 | Directly Financed Air Travel | 1,955.05 |
| 2008 | 3 | Solid Waste | -18.18 |
| 2008 | 3 | T&D Losses | 351.38 |
| 2009 | 1 | Co-gen Electricity | 1,883.62 |
| 2009 | 1 | Co-gen Steam | 1,883.75 |
| 2009 | 1 | Other On-Campus Stationary | 5,338.58 |
| 2009 | 1 | Direct Transportation | 171.13 |
| 2009 | 1 | Refrigerants & Chemicals | 254.40 |
| 2009 | 2 | Purchased Electricity | 2,324.12 |
| 2009 | 3 | Directly Financed Air Travel | 1,829.63 |
| 2009 | 3 | Solid Waste | -21.65 |
| 2009 | 3 | T&D Losses | 229.86 |
| 2010 | 1 | Co-gen Electricity | 1,914.42 |
| 2010 | 1 | Co-gen Steam | 1,250.02 |
| 2010 | 1 | Other On-Campus Stationary | 4,634.89 |
| 2010 | 1 | Direct Transportation | 172.35 |
| 2010 | 1 | Refrigerants & Chemicals | 268.98 |
| 2010 | 2 | Purchased Electricity | 2,674.72 |
| 2010 | 3 | Faculty Commuting | 493.58 |
| 2010 | 3 | Staff Commuting | 1,348.64 |
| 2010 | 3 | Directly Financed Air Travel | 1,397.91 |
| 2010 | 3 | Solid Waste | -21.57 |
| 2010 | 3 | T&D Losses | 165.32 |
| 2011 | 1 | Co-gen Electricity | 2,983.95 |
| 2011 | 1 | Co-gen Steam | 3,128.64 |
| 2011 | 1 | Other On-Campus Stationary | 4,431.87 |
| 2011 | 1 | Direct Transportation | 157.84 |
| 2011 | 1 | Refrigerants & Chemicals | 344.02 |
| 2011 | 2 | Purchased Electricity | 975.67 |
| 2011 | 3 | Faculty Commuting | 649.56 |
| 2011 | 3 | Staff Commuting | 1,444.60 |
| 2011 | 3 | Directly Financed Air Travel | 1,480.45 |
| 2011 | 3 | Solid Waste | -20.00 |
| 2011 | 3 | Paper Purchasing | 48.92 |
| 2011 | 3 | T&D Losses | 60.30 |
| 2012 | 1 | Co-gen Electricity | 1,363.35 |
| 2012 | 1 | Co-gen Steam | 1,090.79 |
| 2012 | 1 | Other On-Campus Stationary | 4,471.94 |
| 2012 | 1 | Direct Transportation | 159.78 |
| 2012 | 1 | Refrigerants & Chemicals | 212.49 |
| 2012 | 2 | Purchased Electricity | 2,345.47 |
| 2012 | 3 | Faculty Commuting | 936.78 |
| 2012 | 3 | Staff Commuting | 1,517.95 |
| 2012 | 3 | Directly Financed Air Travel | 1,338.69 |
| 2012 | 3 | Solid Waste | -4.68 |
| 2012 | 3 | Paper Purchasing | 54.76 |
| 2012 | 3 | T&D Losses | 236.80 |
| 2013 | 1 | Co-gen Electricity | 3,160.94 |
| 2013 | 1 | Co-gen Steam | 2,435.84 |
| 2013 | 1 | Other On-Campus Stationary | 4,255.93 |
| 2013 | 1 | Direct Transportation | 166.32 |
| 2013 | 1 | Refrigerants & Chemicals | 59.56 |
| 2013 | 2 | Purchased Electricity | 850.78 |
| 2013 | 3 | Faculty Commuting | 451.69 |
| 2013 | 3 | Staff Commuting | 1,418.60 |
| 2013 | 3 | Directly Financed Air Travel | 1,118.34 |
| 2013 | 3 | Solid Waste | -3.62 |
| 2013 | 3 | T&D Losses | 85.90 |
| 2014 | 1 | Co-gen Electricity | 2,774.18 |
| 2014 | 1 | Co-gen Steam | 2,785.24 |
| 2014 | 1 | Other On-Campus Stationary | 3,938.55 |
| 2014 | 1 | Direct Transportation | 155.63 |
| 2014 | 1 | Refrigerants & Chemicals | 31.99 |
| 2014 | 2 | Purchased Electricity | 191.76 |
| 2014 | 3 | Faculty Commuting | 406.85 |
| 2014 | 3 | Staff Commuting | 1,226.65 |
| 2014 | 3 | Directly Financed Air Travel | 1,766.06 |
| 2014 | 3 | Solid Waste | -22.75 |
| 2014 | 3 | T&D Losses | 10.03 |
| 2015 | 1 | Co-gen Electricity | 2,080.21 |
| 2015 | 1 | Co-gen Steam | 2,177.75 |
| 2015 | 1 | Other On-Campus Stationary | 4,215.38 |
| 2015 | 1 | Direct Transportation | 139.26 |
| 2015 | 1 | Refrigerants & Chemicals | 31.99 |
| 2015 | 2 | Purchased Electricity | 642.19 |
| 2015 | 3 | Faculty Commuting | 663.64 |
| 2015 | 3 | Staff Commuting | 1,298.95 |
| 2015 | 3 | Directly Financed Air Travel | 2,015.18 |
| 2015 | 3 | Solid Waste | -27.16 |
| 2015 | 3 | T&D Losses | 33.59 |
| 2016 | 1 | Co-gen Electricity | 2,342.06 |
| 2016 | 1 | Co-gen Steam | 2,346.06 |
| 2016 | 1 | Other On-Campus Stationary | 4,039.75 |
| 2016 | 1 | Direct Transportation | 118.05 |
| 2016 | 1 | Refrigerants & Chemicals | 4.77 |
| 2016 | 2 | Purchased Electricity | 563.99 |
| 2016 | 3 | Faculty Commuting | 636.80 |
| 2016 | 3 | Staff Commuting | 1,482.84 |
| 2016 | 3 | Directly Financed Air Travel | 1,679.88 |
| 2016 | 3 | Solid Waste | 3.30 |
| 2016 | 3 | T&D Losses | 26.51 |
| 2017 | 1 | Co-gen Electricity | 2,742.82 |
| 2017 | 1 | Co-gen Steam | 2,493.93 |
| 2017 | 1 | Other On-Campus Stationary | 3,993.50 |
| 2017 | 1 | Direct Transportation | 119.93 |
| 2017 | 1 | Refrigerants & Chemicals | 4.77 |
| 2017 | 2 | Purchased Electricity | 330.05 |
| 2017 | 3 | Faculty Commuting | 1,273.76 |
| 2017 | 3 | Staff Commuting | 679.34 |
| 2017 | 3 | Directly Financed Air Travel | 1,656.04 |
| 2017 | 3 | Solid Waste | 3.26 |
| 2017 | 3 | T&D Losses | 15.52 |
| 2018 | 1 | Co-gen Electricity | 1,731.87 |
| 2018 | 1 | Co-gen Steam | 1,755.44 |
| 2018 | 1 | Other On-Campus Stationary | 4,508.93 |
| 2018 | 1 | Direct Transportation | 127.89 |
| 2018 | 1 | Refrigerants & Chemicals | 4.77 |
| 2018 | 2 | Purchased Electricity | 1,729.71 |
| 2018 | 3 | Faculty Commuting | 535.62 |
| 2018 | 3 | Staff Commuting | 1,312.77 |
| 2018 | 3 | Directly Financed Air Travel | 1,847.04 |
| 2018 | 3 | Solid Waste | 3.11 |
| 2018 | 3 | T&D Losses | 88.78 |
| 2019 | 1 | Co-gen Electricity | 2,416.31 |
| 2019 | 1 | Co-gen Steam | 2,637.48 |
| 2019 | 1 | Other On-Campus Stationary | 4,507.55 |
| 2019 | 1 | Direct Transportation | 140.47 |
| 2019 | 1 | Refrigerants & Chemicals | 4.77 |
| 2019 | 2 | Purchased Electricity | 594.09 |
| 2019 | 3 | Faculty Commuting | 563.69 |
| 2019 | 3 | Staff Commuting | 1,284.98 |
| 2019 | 3 | Directly Financed Air Travel | 1,564.56 |
| 2019 | 3 | Solid Waste | 3.03 |
| 2019 | 3 | T&D Losses | 31.93 |
| 2020 | 1 | Co-gen Electricity | 2,732.28 |
| 2020 | 1 | Co-gen Steam | 2,692.80 |
| 2020 | 1 | Other On-Campus Stationary | 3,550.71 |
| 2020 | 1 | Direct Transportation | 91.54 |
| 2020 | 1 | Refrigerants & Chemicals | 4.77 |
| 2020 | 2 | Purchased Electricity | 581.91 |
| 2020 | 3 | Faculty Commuting | 166.00 |
| 2020 | 3 | Staff Commuting | 385.02 |
| 2020 | 3 | Directly Financed Air Travel | 513.51 |
| 2020 | 3 | Solid Waste | 2.57 |
| 2020 | 3 | T&D Losses | 32.57 |