2004 | 1 | Co-gen Electricity | 107,641.60 |
2004 | 1 | Co-gen Steam | 91,700.42 |
2004 | 1 | Other On-Campus Stationary | 3,906.49 |
2004 | 1 | Direct Transportation | 1,672.35 |
2004 | 2 | Purchased Electricity | 40,180.81 |
2004 | 3 | Faculty Commuting | 3,591.10 |
2004 | 3 | Staff Commuting | 16,898.34 |
2004 | 3 | Student Commuting | 23,502.06 |
2004 | 3 | Solid Waste | 2,135.10 |
2004 | 3 | T&D Losses | 3,973.93 |
2005 | 1 | Co-gen Electricity | 93,819.98 |
2005 | 1 | Co-gen Steam | 88,450.29 |
2005 | 1 | Other On-Campus Stationary | 3,762.95 |
2005 | 1 | Direct Transportation | 1,663.99 |
2005 | 2 | Purchased Electricity | 48,496.21 |
2005 | 3 | Faculty Commuting | 3,669.04 |
2005 | 3 | Staff Commuting | 17,417.31 |
2005 | 3 | Student Commuting | 22,513.12 |
2005 | 3 | Directly Financed Air Travel | 8,340.69 |
2005 | 3 | Solid Waste | 2,120.86 |
2005 | 3 | T&D Losses | 4,796.33 |
2006 | 1 | Co-gen Electricity | 69,242.14 |
2006 | 1 | Co-gen Steam | 92,506.06 |
2006 | 1 | Other On-Campus Stationary | 2,916.46 |
2006 | 1 | Direct Transportation | 1,853.80 |
2006 | 2 | Purchased Electricity | 83,193.78 |
2006 | 3 | Faculty Commuting | 4,410.93 |
2006 | 3 | Staff Commuting | 19,914.73 |
2006 | 3 | Student Commuting | 21,347.51 |
2006 | 3 | Directly Financed Air Travel | 9,294.88 |
2006 | 3 | Solid Waste | 2,113.49 |
2006 | 3 | T&D Losses | 8,227.96 |
2007 | 1 | Co-gen Electricity | 84,106.07 |
2007 | 1 | Co-gen Steam | 88,424.43 |
2007 | 1 | Other On-Campus Stationary | 2,538.72 |
2007 | 1 | Direct Transportation | 1,622.39 |
2007 | 2 | Purchased Electricity | 83,868.34 |
2007 | 3 | Faculty Commuting | 4,373.70 |
2007 | 3 | Staff Commuting | 20,369.75 |
2007 | 3 | Student Commuting | 20,353.78 |
2007 | 3 | Directly Financed Air Travel | 8,600.25 |
2007 | 3 | Solid Waste | 2,266.76 |
2007 | 3 | T&D Losses | 8,294.67 |
2008 | 1 | Co-gen Electricity | 73,568.43 |
2008 | 1 | Co-gen Steam | 96,461.59 |
2008 | 1 | Other On-Campus Stationary | 3,473.47 |
2008 | 1 | Direct Transportation | 1,467.92 |
2008 | 2 | Purchased Electricity | 99,886.50 |
2008 | 3 | Faculty Commuting | 4,393.45 |
2008 | 3 | Staff Commuting | 20,384.00 |
2008 | 3 | Student Commuting | 20,424.43 |
2008 | 3 | Directly Financed Air Travel | 9,207.17 |
2008 | 3 | Study Abroad Air Travel | 2,180.28 |
2008 | 3 | Solid Waste | 2,195.50 |
2008 | 3 | T&D Losses | 9,878.88 |
2009 | 1 | Co-gen Electricity | 86,927.13 |
2009 | 1 | Co-gen Steam | 70,797.14 |
2009 | 1 | Other On-Campus Stationary | 3,191.08 |
2009 | 1 | Direct Transportation | 1,459.40 |
2009 | 2 | Purchased Electricity | 122,436.59 |
2009 | 3 | Faculty Commuting | 3,649.00 |
2009 | 3 | Staff Commuting | 18,049.68 |
2009 | 3 | Student Commuting | 20,752.12 |
2009 | 3 | Directly Financed Air Travel | 8,412.80 |
2009 | 3 | Study Abroad Air Travel | 967.72 |
2009 | 3 | Solid Waste | 1,979.91 |
2009 | 3 | T&D Losses | 12,109.11 |
2010 | 1 | Co-gen Electricity | 77,123.67 |
2010 | 1 | Co-gen Steam | 69,666.20 |
2010 | 1 | Other On-Campus Stationary | 2,610.46 |
2010 | 1 | Direct Transportation | 1,446.78 |
2010 | 2 | Purchased Electricity | 122,813.52 |
2010 | 3 | Faculty Commuting | 3,702.71 |
2010 | 3 | Staff Commuting | 18,268.87 |
2010 | 3 | Student Commuting | 21,979.93 |
2010 | 3 | Directly Financed Air Travel | 8,613.73 |
2010 | 3 | Study Abroad Air Travel | 1,004.40 |
2010 | 3 | Solid Waste | 1,540.63 |
2010 | 3 | T&D Losses | 7,590.84 |
2011 | 1 | Co-gen Electricity | 82,101.34 |
2011 | 1 | Co-gen Steam | 72,967.47 |
2011 | 1 | Other On-Campus Stationary | 2,142.09 |
2011 | 1 | Direct Transportation | 1,437.68 |
2011 | 2 | Purchased Electricity | 120,613.48 |
2011 | 3 | Faculty Commuting | 3,776.04 |
2011 | 3 | Staff Commuting | 17,472.06 |
2011 | 3 | Student Commuting | 14,640.63 |
2011 | 3 | Directly Financed Air Travel | 9,281.58 |
2011 | 3 | Study Abroad Air Travel | 1,030.81 |
2011 | 3 | Solid Waste | 1,513.85 |
2011 | 3 | T&D Losses | 7,454.86 |
2012 | 1 | Co-gen Electricity | 71,106.46 |
2012 | 1 | Co-gen Steam | 71,838.83 |
2012 | 1 | Other On-Campus Stationary | 1,960.38 |
2012 | 1 | Direct Transportation | 1,154.35 |
2012 | 2 | Purchased Electricity | 109,635.78 |
2012 | 3 | Faculty Commuting | 3,731.49 |
2012 | 3 | Staff Commuting | 17,155.46 |
2012 | 3 | Student Commuting | 14,244.61 |
2012 | 3 | Directly Financed Air Travel | 8,987.07 |
2012 | 3 | Study Abroad Air Travel | 1,139.79 |
2012 | 3 | Solid Waste | 2,289.97 |
2012 | 3 | T&D Losses | 11,069.02 |
2013 | 1 | Co-gen Electricity | 53,388.78 |
2013 | 1 | Co-gen Steam | 88,707.54 |
2013 | 1 | Other On-Campus Stationary | 2,382.79 |
2013 | 1 | Direct Transportation | 1,389.18 |
2013 | 2 | Purchased Electricity | 128,747.48 |
2013 | 3 | Faculty Commuting | 3,805.98 |
2013 | 3 | Staff Commuting | 17,126.66 |
2013 | 3 | Student Commuting | 14,225.17 |
2013 | 3 | Directly Financed Air Travel | 7,462.22 |
2013 | 3 | Study Abroad Air Travel | 863.60 |
2013 | 3 | Solid Waste | 2,193.80 |
2013 | 3 | T&D Losses | 12,998.57 |
2014 | 1 | Co-gen Electricity | 66,213.42 |
2014 | 1 | Co-gen Steam | 88,671.46 |
2014 | 1 | Other On-Campus Stationary | 2,683.75 |
2014 | 1 | Direct Transportation | 1,387.23 |
2014 | 2 | Purchased Electricity | 108,930.44 |
2014 | 3 | Faculty Commuting | 3,846.63 |
2014 | 3 | Staff Commuting | 17,533.24 |
2014 | 3 | Student Commuting | 14,443.13 |
2014 | 3 | Directly Financed Air Travel | 6,065.31 |
2014 | 3 | Study Abroad Air Travel | 780.56 |
2014 | 3 | Solid Waste | 2,243.98 |
2014 | 3 | T&D Losses | 6,076.44 |
2015 | 1 | Co-gen Electricity | 56,738.08 |
2015 | 1 | Co-gen Steam | 83,005.65 |
2015 | 1 | Other On-Campus Stationary | 2,346.58 |
2015 | 1 | Direct Transportation | 1,312.50 |
2015 | 2 | Purchased Electricity | 122,811.68 |
2015 | 3 | Faculty Commuting | 3,945.06 |
2015 | 3 | Staff Commuting | 17,166.43 |
2015 | 3 | Student Commuting | 14,231.74 |
2015 | 3 | Directly Financed Air Travel | 3,691.28 |
2015 | 3 | Study Abroad Air Travel | 1,139.56 |
2015 | 3 | Solid Waste | 2,267.85 |
2015 | 3 | T&D Losses | 6,422.96 |
2016 | 1 | Co-gen Electricity | 48,485.19 |
2016 | 1 | Co-gen Steam | 74,937.07 |
2016 | 1 | Other On-Campus Stationary | 2,214.34 |
2016 | 1 | Direct Transportation | 1,184.87 |
2016 | 2 | Purchased Electricity | 104,888.94 |
2016 | 3 | Faculty Commuting | 3,859.05 |
2016 | 3 | Staff Commuting | 17,062.08 |
2016 | 3 | Student Commuting | 14,332.04 |
2016 | 3 | Directly Financed Air Travel | 3,584.21 |
2016 | 3 | Study Abroad Air Travel | 418.06 |
2016 | 3 | Solid Waste | 2,431.42 |
2016 | 3 | T&D Losses | 4,930.91 |
2017 | 1 | Co-gen Electricity | 32,940.16 |
2017 | 1 | Co-gen Steam | 78,589.80 |
2017 | 1 | Other On-Campus Stationary | 2,285.53 |
2017 | 1 | Direct Transportation | 1,353.62 |
2017 | 2 | Purchased Electricity | 139,993.86 |
2017 | 3 | Faculty Commuting | 1,531.37 |
2017 | 3 | Staff Commuting | 6,100.97 |
2017 | 3 | Student Commuting | 8,134.01 |
2017 | 3 | Directly Financed Air Travel | 7,480.07 |
2017 | 3 | Study Abroad Air Travel | 320.64 |
2017 | 3 | Solid Waste | 2,148.74 |
2017 | 3 | T&D Losses | 6,581.22 |
2018 | 1 | Co-gen Electricity | 41,377.04 |
2018 | 1 | Co-gen Steam | 81,371.18 |
2018 | 1 | Other On-Campus Stationary | 2,865.79 |
2018 | 1 | Direct Transportation | 1,018.92 |
2018 | 2 | Purchased Electricity | 122,521.69 |
2018 | 3 | Faculty Commuting | 1,544.99 |
2018 | 3 | Staff Commuting | 6,286.65 |
2018 | 3 | Student Commuting | 8,492.87 |
2018 | 3 | Directly Financed Air Travel | 7,446.66 |
2018 | 3 | Study Abroad Air Travel | 1,363.43 |
2018 | 3 | Solid Waste | 2,199.84 |
2018 | 3 | T&D Losses | 6,288.48 |
2019 | 1 | Co-gen Electricity | 62,193.69 |
2019 | 1 | Co-gen Steam | 78,703.75 |
2019 | 1 | Other On-Campus Stationary | 3,505.01 |
2019 | 1 | Direct Transportation | 1,097.04 |
2019 | 2 | Purchased Electricity | 88,225.70 |
2019 | 3 | Faculty Commuting | 1,582.63 |
2019 | 3 | Staff Commuting | 6,415.41 |
2019 | 3 | Student Commuting | 8,677.71 |
2019 | 3 | Directly Financed Air Travel | 4,383.69 |
2019 | 3 | Study Abroad Air Travel | 950.96 |
2019 | 3 | Solid Waste | 2,090.09 |
2019 | 3 | T&D Losses | 4,741.32 |
2020 | 1 | Co-gen Electricity | 71,960.99 |
2020 | 1 | Co-gen Steam | 65,808.43 |
2020 | 1 | Other On-Campus Stationary | 1,108.42 |
2020 | 1 | Direct Transportation | 1,033.78 |
2020 | 2 | Purchased Electricity | 70,429.67 |
2020 | 3 | Faculty Commuting | 674.61 |
2020 | 3 | Staff Commuting | 4,780.12 |
2020 | 3 | Student Commuting | 4,742.47 |
2020 | 3 | Directly Financed Air Travel | 6,038.23 |
2020 | 3 | Study Abroad Air Travel | 330.41 |
2020 | 3 | Solid Waste | 1,757.06 |
2020 | 3 | T&D Losses | 4,197.11 |
2021 | 1 | Co-gen Electricity | 69,017.39 |
2021 | 1 | Co-gen Steam | 64,674.42 |
2021 | 1 | Other On-Campus Stationary | 1,062.70 |
2021 | 1 | Direct Transportation | 918.02 |
2021 | 2 | Purchased Electricity | 74,555.29 |
2021 | 3 | Faculty Commuting | 445.32 |
2021 | 3 | Staff Commuting | 2,679.41 |
2021 | 3 | Student Commuting | 1,480.92 |
2021 | 3 | Directly Financed Air Travel | 338.83 |
2021 | 3 | Solid Waste | 1,454.39 |
2021 | 3 | T&D Losses | 4,172.58 |